Question -

  • The time required to do a job varies inversely to the number of people working. It takes 5 hours for 7 carpenters to build a retaining wall. How long will it take for 10 carpenters to complete the job?

★ Answer -

  • 10 carpenters will take 3.5 hours to build the retaining wall.

Step-by-step explanation -

  • In this question, it is given that it takes 5 hours for 7 carpenters to build a retaining wall. We have to find the time that will be taken by 10 carpenters to complete the job.

Let -

  • The time taken by 10 carpenters to complete the job be "x" hours.

Given that -

  • The time required to do the job varies inversely to the number of people working.

We know that -

  • When two quantities "x" and "y" are in inverse variation, xy is constant.

Therefore -

 \sf \implies xy \: is \: constant

 \implies \sf 10 \times x = 7 \times 5

  \sf \implies 10x = 35

 \implies \sf x =   \cancel\dfrac{35}{10}

 \implies \sf x =  \dfrac{7}{2}

 \implies \sf x = 3.5

 \\

Hence -

  • 10 carpenters will take 3.5 hours to build the retaining wall.