Ntse MAT question A is 3 times more efficient than B. Hence, he takes 60 days less in painting a room. In how many days, work will be completed, if A and B both work together? (1) 30 days (2) 45 days (3) 22 1 2 days (4) 17 1 2 days
Answers
Answered by
16
The answer is (3)
Efficiency A : B
n = 3n
3n - n = 60
n = 30
A = 30, B = 90
(A + B) = (30*90)/120=22 1/2 Days
Efficiency A : B
n = 3n
3n - n = 60
n = 30
A = 30, B = 90
(A + B) = (30*90)/120=22 1/2 Days
Answered by
7
Answer:
Step-by-step explanation:
We are given that A is 3 times more efficient than B
Let A completes work in x days
So, B completes work in 3x days
A takes 60 less days than B
So, 3x-x = 60
2x=60
x=30 days
So, A complete work in 30 days
A 's 1 day work =
B complete work in 90 days
B's 1 day work =
So, they do work together in 1 day =
So, they complete work together =
Hence A and B both work together in