If a man can complete a work in 12 days and
woman can complete the same work in 18 days
.Find the time taken by 4 men and 6 woman to
complete the work.
А.
2.4 days
B
1.5 days
С
3 days
D
3.4 days
Answers
Answered by
1
Answer:
mark my answer Brainliest
Step-by-step explanation:
option c is the answer I hope it will help you best of luck
Answered by
1
Answer:
C. 3 days.
Step By step explanation★
=> a man can complete a work in 12 days. It means that if we divide the work in 12 days so each day a part of work is completed by a man... So , If 1 man is completing 1 part of work so 4 men will complete 4 parts of the work in 1 day so the work will be completed in 3 days. Same explanation goes for women.