of a certain work in 12 days and
2
3. A can do
1
can do
of the same work in 4 days. Both
6
and B together can complete the work in:
Answers
Answered by
9
Answer:
Time taken by both A and B to complete full work will be 10(2/7) days.
Step-by-step explanation:
A can do 2/3 of the work in 12 days
=> A can do full work in = 12 x 3/2 = 18 days
=> work done by A in one day = 1/18
B can do 1/6 of work in 4 days
=> B can do full work in = 4 x 6 = 24 days
=> work done by B in one day = 1/24
Hence work done by both A and B in one day together
= 1/18 + 1/24
= 7/72
So time taken by both A and B to complete full work = 72/7 = 10(2/7) days.
Similar questions
Social Sciences,
5 months ago
English,
5 months ago
Math,
5 months ago
Math,
10 months ago
Computer Science,
1 year ago