On completing a work john mark journey at a total of 841$ how much should join be paid john and mark together complete 11/29 of the work jimmy and mark together completed 19 by 29th of the work
Answers
Answered by
0
Answer:
It seems there is some problem with this question.
Let the distance between A and B is D km. As Paul is faster, take the speeds of Jake and Paul are s and 3s kmph.
As the speeds are in the ratio of 1 : 3, times taken by them should be 3 : 1. Take the times taken by them are 3x , x. But We know that 3x - x = 2 hour 15 min. So 2x = 9/4 hours, x = 9/8 hours. So time taken by the slower one (Jake) takes 3x time = 3 x 9/8 = 27/8 hours = 202.5 minutes.
(Or)
Take Jake speed = j and Paul = p kmph.
Now given that Dj−Dp = 2 hr 15 min = 214 hrs = 9/4 hrs
Also both of them together covered D distance in 2 hours. So Dj+Dp=2
Adding these two equations will give us 2Dj=94+2=174 = 4 hours 15 minutes.
So in the above problem, some part is redundant.
Similar questions