Math, asked by faraz2920, 11 months ago

One-half of a road construction project was completed by 6 workers in 12 days. Working at the same rate, what is the smallest number of workers needed to finish the rest of the project in exactly four days?

Answers

Answered by AvinashNanganure
0

Answer:

16 workers

Step-by-step explanation:

let X be the time required to complete work by one man

rate of doing work = 1/X

6 * 12 = 1

----------. ----

x. 2

X = 144days

y * 4 = 1

-------. ---

X 2

y = 144 / 8 = 16 workers