Math, asked by waqasalighsno3, 6 months ago

One person can complete a piece of work in eight days while the other can
complete the same work in four days. (If both work 10 hours per day). How
many hours are required to complete the same work if both persons do the
same combined?
(A) 50 hours, 30 minutes (B) 26 hours, 40 minutes
(C) 42 hours, 15 minutes: (D) 60 hours​

Answers

Answered by rohit73419238
0

Answer:

B

Step-by-step explanation:

this is the answer ok ?

Answered by puzzlepedia
0

Answer:

26 hrs

Step-by-step explanation: