Biology, asked by sidhart2773, 1 year ago

order type-dependent parameters are missing for order type yrf1 in plant 2200message no. co490

Answers

Answered by aksh173
0
For process order you need to maintain the Process Order Type Dependent Paramters in COR4.

Goto COR4-Select your Order Type -For example if it process order then PI01-Now matain the Order type denedent parametrs against that order type .

Mainly :

Master Date :

1.Selection Of PV- Automatic

2.Reciepe selction parameters -Selection id -04/Manual or automatic selection ./Approval required or not etc

2.Process Data Documentiaion -Order Record required

3.Operation Entry -0010

Planning :

BOM Application : Process Manufacturing .

Bastch Serach Procedure : Std CO Procedure .Check Batch Active .

Implementation :

Status Change Doc ( Mark as applicable )

Goods Movement : Std Profile .

Controilling : Stad Costing Variant-If you are using PCC then it will PPP3 /Actual Costing Variant -PPP3 /Result analysis key-00001-Calcualtion in actual cost . Distribution Rule : PP Dsitribution Rule

Based on this above parametrs , while creation of Process order of any type like PI01 or customised Process Order type , master date specially Reciepe , PV all awill be seleced and system will not through error messge s,

Note :

Additionally , you should have the following set up also to complete the PP-PI cycle :

1.Maintain Production Schedeuling Profile in CORY for process Order .

2.Operation Cosnfirmation Paramters in OPK4

3.Scheduling Paramters in OPUZ

Check all of them and compare with your std one .

Try and revert