our workforce of 210 manth is a contractor can finish a work in 16 months how many more Men should be employed so that the work is completed in 14 months
Answers
Answered by
2
Answer:
30
Step-by-step explanation:
no of men=x1=210
time taken to finish the work=y1=16months
no of men required =x2=?
time taken to complete the work y2=14months
men is inversely proportional to time
x1y1=x2y2
210*16=x2 * 14
x2=210*16/14
=240men
no of more men required = 240--210
=30
Answered by
1
who are you.......... .......
Similar questions