Math, asked by ayushnegi878787, 7 months ago

our workforce of 210 manth is a contractor can finish a work in 16 months how many more Men should be employed so that the work is completed in 14 months​

Answers

Answered by gopalpvr
2

Answer:

30

Step-by-step explanation:

no of men=x1=210

time taken to finish the work=y1=16months

no of men required =x2=?

time taken to complete the work y2=14months

men is inversely proportional to time

x1y1=x2y2

210*16=x2 * 14

x2=210*16/14

=240men

no of more men required = 240--210

=30