p alone can complete a work in 10 days and q alone can complete the same work in 20 days if p and q work together then in how many days the same work will be completed
Answers
p and q can complete the work in 6 2/3 days
Given:
p alone can complete a work in 10 days
q alone can complete the same work in 20 days
To find:
If p and q work together then in how many days the same work will be completed
Solution:
p alone can complete a work in 10 days
⇒ Then the work can be done by p in 1 day = 1/10
q alone can complete a work in 20 days
⇒ Then the work can be done by q in 1 day = 1/20
If they both started working together
The work can be done in one day
= = =
p and q can do work in 1 day
The number of days to complete 1 work = = = 6 2/3 days
p and q can complete the work in 6 2/3 days
#SPJ2
Answer:
The answer to the given question is that p and q can complete the work in
Step-by-step explanation:
Given :
p alone can complete a work in 10 days.
q alone can complete the same work in 20 days.
To find :
How many days the same work will be completed if p and q work together?
Solution :
p alone can complete a work in 10 days.
The work can be done by p in 1 day is
q alone can complete a work in 20 days.
The work that can be completed by q in one day is
The work done by both of them, if they start working together means
The work done by both of them in one day is
The days required to complete 1 work is
On division, we get the value as
Therefore, the p and q can complete one work in
# spj5
we can find similar questions through the link given below
https://brainly.in/question/22072413?referrer=searchResults