P and Q agreed to complete a job in 15 days for Rs 6200. P can complete same job in 50 days Q in 30 days.
They had to take R to complete the work in time Find R's share in money earned by them.
Answers
Answered by
3
#BAL
Ans:
Rs.
1240
P and Q together can do the work in
50
×
30
50
+
30
=
75
4
days.
Therefore, in
15
days, P and Q together did
4
75
×
15
=
4
5
of the work.
and R did the remaining
1
5
of work.
R's share
=
6200
×
1
5
=
1240