P and Q can do a piece of work in 12 days and 15 days respectively.p started the work alone then ,after 3 days Q joined him till the work was completed.how long did the work last?
Answers
Answered by
8
In 1- day both together A and B can do = 1/12+1/16 = (4+3)/48= 7/48 -part of the work.
Therefore x/12 + (9-x)7/48 = 1
Upon solving we get 4x + 63–7x= 48
= 3x= 15;
So x= 5
So if “Q” joins after 5- days with“B” the work will be completed in 9- days.