P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?
A) 9 days B) 27 days C) 36 days D) 18 days
Answers
Answered by
1
Answer:
P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together
Step-by-step explanation:
B) 27 days
Answered by
9
YOUR ANSWER IS,
OPTION [B] 27 days