Math, asked by gaznaferali8048, 9 months ago

P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together?

A) 9 days B) 27 days C) 36 days D) 18 days

Answers

Answered by lisaRohan
1

Answer:

P and Q can do a project in 60 and 30 days respectively. In how many days can they complete 90% of the project if they work together

Step-by-step explanation:

B) 27 days

Answered by SɴᴏᴡʏSᴇᴄʀᴇᴛ
9

\huge\bf\red{Hello\:Mate}

YOUR ANSWER IS,

OPTION [B] 27 days