Math, asked by knrajput7519, 10 months ago

P and q can do a work in 12 days and 16 days respectively p started the work alone after how many days should q join p so that the work is finished in 9 days

Answers

Answered by venupillai
0

Answer:

Q should join P after 5 days so that work is completed in 9 days.

Step-by-step explanation:

P can do the work in 12 days

=> Fraction of work done by P in 1 day = 1/12

Q can do the work alone in 16 days

=> Fraction of work done by Q in 1 day = 1/16

When P and Q work together,

Fraction of work done by P+Q in 1 day = 1/12 + 1/16  = 7/48

Let us assume that P works alone for "x" days.

As the work needs to be completed in 9 days, Q will join after (9 - x) days.

This means:

P will work alone for x days

P+Q will work together for (9 - x) days

Fraction of work done by P in "x" days = x/12

Fraction of work done by (P+Q) in (9-x) days = (7/48)*(9 - x)

Both these fractions when added represented completion of work

=> \frac{x}{12} + \frac{7*(9-x)}{48} = 1

=> 4x + 7*(9 - x) = 48

=> 4x + 63 - 7x = 48

=> -3x = -15

=> x = 5

P should work alone for 5 days and Q should join on the 6th day.

Final answer: Q should join P after 5 days so that work is completed in 9 days.

Similar questions