P and Q can Finish a Work in 30days they work Together for 10 days And The Q left. The remaining work is done by P alone in 20 more days. How Long will P take To Complete The Whole Work alone ? Explain​

Answers

Answered by aman144219
0

Answer:

60 days is the correct answer