P and q can finish the work in 6 days and q and R together can finish the same work in 60 /7 days working together whereas R and P can finish the same work in 20/3 days working together in how much time can be P, Q, R finish the same work if all of them work together
Answers
Answered by
0
Answer:
ok
Step-by-step explanation:
Answered by
0
Answer:
this ur solution ok follow me
Step-by-step explanation:
Let the work be considered to have 36- units.
In 1- day P+Q can do=36/18= 2- units
In 1- day P+R can do= 36/12=3- units
In 1- day R+S can do= 36/9= 4- units
So P+ Q+ R can do in 1- day= (2+3+4)/2 = 4.5- units
So in 1- day Q- alone can = (4.5- 3) =1.5-units.
Therefore Q can complete the work alone in = 36/1.5= 24- days.