P and q together can do work in 18 days .P alone can do same work in 27 days in how many days can q alone do same work
Answers
Answered by
9
wen we do p and q together it answer come 45
Answered by
14
Answer:
q alone can do a piece of work in 54 days.
Step-by-step explanation:
P and q together can do work in 18 days.
P alone can do same work in 27 days.
We need to find in how many days q alone can do the same work?
Step 1- First we need to find the L.C.M of 18 and 27 which is 54.
Therefore Efficiency of (p+q) = 3
Efficiency of p = 2
Step 2- Efficiency of q = Efficiency of (p + q) - Efficiency of (p)
= 3 - 2
= 1
Step 3- q alone can do a piece of work in =
= 54 days
Hence q alone can do a piece of work in 54 days.