P and Q working together can complete a job in 48 days. the ratio of their rates of doing work is 3:5. Find the time taken by the faster person to complete the job
Answers
Answered by
0
Answer:
6 days
Step-by-step explanation:
3x + 5x = 48 days
8x = 48 days
Now , x = 48
••••• = 6 days
8
So the time taken by faster person is 6 days.