Math, asked by ravikumar6769, 9 months ago

P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work?​

Answers

Answered by BRAINLYARMY001
2

Answer:

hi

your answer is here !

Step-by-step explanation:

P can complete the work in (12 x 8) hrs = 96 hrs

Q can complete the work in (8 x 10) hrs=80 hrs

Therefore, P's 1 hour work=1/96 and Q's 1 hour work= 1/80

(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs

Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11

follow \:  \:  \: me

Similar questions