P can complete a work in 6 days. Working with the help of q, the job is completed in 7 days. If p starts the work and p and q work on alternate days, in how many days can q alone complete the job?

Answers

Answered by feminmg
9

Answer:

Step-by-step explanation:

I also got this question in rrb je

P alone do it in 6 day's

With the help of q it takes more time ie, 7 days

Which is Unusual p+q should do the job in less than 6 days

If you have any answer please share

Answered by rapellyramesh8
5

Answer:

Step-by-step explanation: