Math, asked by rishibhushan, 1 year ago

P can do a job in 15 days in how many days can P and Q together complete the job if Q is twice as fast as p

Answers

Answered by praneethks
11

Step-by-step explanation:

P can do a job in 15 days.

It is given that Q is twice as fast as P.

Q can do a job in 15/2 days.

No. of days taken by P and Q to complete the job = 1/(1/15+2/15) =1/(3/15) = 5 days. Hope it helps you.

Answered by sharonr
9

In 5 days, P and Q together complete the job if Q is twice as fast as p

Solution:

Given that,

P can do a job in 15 days

Q is twice as fast as p

Therefore,

\text{ Q can do a job in } = \frac{15}{2} = 7.5\ days

How many days can P and Q together complete the job

Together\ complete\ job = \frac{AB}{A+B}

Where,

A is the days taken by P

B is the days taken by Q

Thus,

Together\ complete\ job = \frac{15 \times 7.5}{15+7.5}\\\\Together\ complete\ job = \frac{112.5}{22.5}\\\\Together\ complete\ job =5

Thus in 5 days, P and Q together complete the job if Q is twice as fast as p

Learn more about this topic

P and q together can do a work in 10 days . They worked together for 4 days and q then leaves of p finished the remaining work in 18 days.In how many days can q alone finish the whole work

https://brainly.in/question/6687228

P and Q can together finish a work in 30 days. They worked at it for 20 days and then Q left . The remaining work was done by P alone in 20 more days. In how many days can P alone do it ?​

https://brainly.in/question/8725270

Similar questions