P can do a piece of work in 20 days and Q in 25 days. They worked together for 5 days and then Q left the work.
Find the number of days in which P can finish the remaining work.
Answers
Answered by
1
In 20 days, P can do 1 complete work
In 1 day, P can do 1/20th of the work.
Similarly, Q’s 1 day work=1/25
Therefore, 1 day work of P and Q working together=1/20+1/25=9/100
Therefore, 5 day work of P and Q working together= 9/20
Remaking work=11/20
Number of days required by P to finish the work=(11/20)/(1/20)=11
In 1 day, P can do 1/20th of the work.
Similarly, Q’s 1 day work=1/25
Therefore, 1 day work of P and Q working together=1/20+1/25=9/100
Therefore, 5 day work of P and Q working together= 9/20
Remaking work=11/20
Number of days required by P to finish the work=(11/20)/(1/20)=11
Answered by
1
Answer:
11 days.
Step-by-step explanation:
P does work in 20 days. Q in 25 days.
So, in 1 day P does work = 1/20 ( So, in 20 days it will become 1, that means that his work is done)
Same with Q, 1 day work of Q = 1/25.
The worked together for 5 day.
So, (P + Q)'s 1 day work = 1/20 + 1/25
= 9/100
(P + Q)'s 1*5 day work = 9*5/100 = 9/20.
So, in 5 days 9/20 work was done, remaining work is 1 - 9/20 = 11/20.
Now only P is working.
P's 1*11 day work = 1*11/20
11/20 was the work remaining, which P would do in 11 days.
Similar questions
India Languages,
10 days ago
Geography,
10 days ago
Math,
19 days ago
Math,
9 months ago
Political Science,
9 months ago