Math, asked by deepakpaswan8417, 1 year ago

P can do a work in the same time in which q and r together can do it. if p and q work together, the work can be completed in 10 days. r alone needs 50 days to complete the same work. then q alone can do it in?

Answers

Answered by pinaki2
4
r=1/50
p=q+r
p-q=r
p-q=1/50
p+q=1/10
2p=6/50
p=3/50
q=3/50-1/50=2/50=1/25
q alone can do the work in 25 days.
Answered by anupkumarchakra30
1

Answer:

  • 12 hours

Step-by-step explanation:

Work done by A in 1 hour = 1/4

Work done by B and C in 1 hour = 1/3

Work done by A and C in 1 hour = 1/2

Work done by A,B and C in 1 hour = 1/4+1/3 = 7/12

Work done by B in 1 hour = 7/12 – 1/2 = 1/12 ,,

Hence, B alone can complete the work in 12 hours