P can do piece of work in 12 days and Q can do it in 15 days. In how many days can they finish it, if they work together?
Answers
Answered by
0
Answer:
6
Step-by-step explanation:
here is your solution..............
Attachments:
Answered by
0
Answer:
6 days 16 hours
Step-by-step explanation:
part of work done by P in 1 day = 1/12
part of work done by Q in 1 day = 1/15
therefore,
part of work done by both in 1 day = 1/12 +1/15 = (12+15) / 180 = 27/180 = 3/20
=>
P & Q can do the work in 20/3 days or 6 days 16 hours approx