p completes 80% of a certain work in 20 days. then with the help of Q ,he is able to finish it in 3 more days. How many days will Q take to finish the work, if he works alone ?
Answers
Answer:
Q take 37.5 or 75/2 days to finish the work.
Step-by-step explanation:
Consider the provided information.
P completes 80% of a certain work in 20 days. then with the help of Q ,he is able to finish it in 3 more days.
P completes the 80% of the work in 20 days.
If P work for 20 days then task complete by P is = 80/100 = 4/5
Work done by P in one day is 80/20 = 4%
That means P can complete the whole work in 25 days.
P's 1 day work is = 1/25
Now the remaining work is = 1 - 4/5 = 1/5
Assume that Q can complete the whole work in x days
Q's 1 day work is = 1/x
If they both work together for one day then work done
1/25 + 1/x = (25+x)/25x
As it is given that they work for 3 days, so the work done in 3 days is 3(x+25)/25x
They complete the remaining work which was 1/5.
Hence, Q take 37.5 or 75/2 days to finish the work.