Math, asked by ravneet1028, 6 months ago

P is 1.5 times as efficient as Q. Q takes 5 more days than P to complete the work. It is also known that Q takes 3 days more than R to complete the work. All of them began working but P leaves the work after 2 days from the start and R leaves 3 days before completing the work. How long does it take to complete the work?
6
9
7.5
8.4

Answers

Answered by vinayy12345
2

P is 1.5 times as efficient as Q. Q takes 5 more days than P to complete the work. It is also known that Q takes 3 days more than R to complete the work. All of them began working but P leaves the work after 2 days from the start and R leaves 3 days before completing the work. How long does it take to complete the work?

6

9

7.5

8.4

Answered by kratika25singhdec
2

Step-by-step explanation:

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

Answer

10

Follow

Request

More

You cannot write an answer

You aren't allowed to write answers to questions.

Ad by Dell

Season to start anew.

Celebrate festivities with Dell PCs.

Shop Now

8 Answers

Nahas Ellathu Parambil, HVAC QC Engineer

Answered October 30, 2017

Let B take D no: of days to finish the work.

So, A takes D-8 days to finish.

Efficiency of A = 1/(D-8)

Efficiency of B = 1/D

Given that A is 1.5 times efficient than B.

ie

(1/D-8)/(1/D) = 1.5

or D = 24.

ie in one day A can finish 1/16 of work. B can finish 1/24 of work.

If A and B work on alternate days, they finish 1/16 +1/24 = 5/ 48 of the work in 2 days.

no: of days (alternate) required to finish work = 1/(5/48) = 9.6 days for each person, that is 19.2 days.

Now , we cross check the status after 19 days. A have worked for 10 days and B for 9 days.

Amount of work finished after 19 days = 10 x (1/16) + 9 x (1/24) = 1.

That means, at the end of exactly 19 days, the work would finish.

A work for 10 days and B for 9 days.

The value 19.2 we got is because of the lesser efficiency of B.

Similar questions