P is 30% more efficient than q. p can complete a work in 23 days. if p and q work together, how much time will it take to complete the same work?
Answers
Answered by
0
I think answer 7 days...
p time taken days 6.9
and q is 30 per more than q so, he taken 2.07 days.. both can done work in 7 days..
p time taken days 6.9
and q is 30 per more than q so, he taken 2.07 days.. both can done work in 7 days..
Answered by
4
Answer:
13 days
Step-by-step explanation:
Work done by P in 1 day = 1/23
Let work done by Q in 1 day = q
q × (130/100) = 1/23
=> q = 100/(23×130) = 10/(23×13)
Work done by P and Q in 1 day = 1/23 + 10/(23×13) = 23/(23×13)= 1/13
=> P and Q together can do the work in 13 days