P is 4 times faster than Q in doing a job. Q takes 27 more days than P to finish the job. If they work together, in how many days will the work be finished
Answers
Answer:
36/5 days or 7 \times \frac{1}{5} days
Step-by-step explanation:
Rate(P) = 4 × Rate(Q)
let the total work be = 1 unit
Using, Rate × Time = Work
Time taken by P = 1/Rate(P) = Time(P)
Time taken by Q = 1/Rate(Q) = Time(Q)
Time(Q) - Time(P) = 27
[1/Rate(Q)] - [1/Rate(P)] = 27
[Rate(P) - Rate(Q)]/[Rate(P) × Rate(Q)] = 27
[(4 × Rate(Q)) - Rate(Q)]/[(4 × Rate(Q)) × Rate(Q)] = 27
[3 × Rate(Q)]/[(4 × Rate(Q)) × Rate(Q)] = 27
Rate(Q)/[(4 × Rate(Q)) × Rate(Q)] = 9
1/[4 × Rate(Q)] = 9
1 = 36 × Rate(Q)
Rate(Q) = 1/36
Therefore, Rate(P) = 4 × 1/36 = 1/9
Rate(P) + Rate(Q) = (1/36) + (1/9)
= 5/36 = Rate(P + Q)
Using, Rate × Time = Work
Rate(P + Q) Time(P + Q) = Total Work
(5/36) × Time(P + Q) = 1
Time(P + Q) = 36/5 =
Therefore, if P and Q work together, they will finish work in 36/5 days or days
Please mark answer as brainliest, it will help :)