P, Q and R can do a piece of work in 60 days, 100 days and 80 days respectively. They together work to finish the work and receive INR 2256. Then P will get
Answers
Answered by
4
Answer:
P will Get = Rs 960
Step-by-step explanation:
P, Q and R can do a piece of work in 60 days, 100 days and 80 days respectively. They together work to finish the work and receive INR 2256.
P's 1 day Work = 1/60
Q's 1 Day Work = 1/100
R's 1 day Work = 1/80
Ratio of P:Q:R Works
1/60 : 1/100 : 1/80
Multiplying by 1200 both sides
20 : 12 : 15
20 + 12 + 15 = 47
P's Share = (20/47) * 2256 = Rs 960
Q's Share = (12/47) * 2256 = Rs 576
R's Share = (15/47) * 2256 = Rs 720
P will Get = Rs 960