P,Q and R can do a work in 10,15 and 30 days respectively P works daily Q and R together join P on alternate days starting the first day in how many days will the work be done
Answers
Answered by
7
Answer:6 1/2
Step-by-step explanation:
Lcm=10,15,30=30
30 means 30parts
Starting p+q+r=30/10+30/15+30/30
P+Q+R=6
Alternat day only P=3
For 2 days=9 parts
6days=27 parts
Remaining 3 parts done by p+q+r=3/6day =1/2day
Total work done in 6 1/2 days