P works twice as fast as q. if q alone can complete a work in 12 days, p and q can finish the work in --- days

Answers

Answered by Anonymous
2
please mark it as a brainliest answer
Attachments:
Answered by anuham97
0

Answer:

4 days

Step-by-step explanation:

Work done by Q in 1 day = 1/12

Work done by P in 1 day = 2 × (1/12) = 1/6

Work done by P and Q in 1 day = 1/12 + 1/6 = ¼

=> P and Q can finish the work in 4 days