Pam can complete a job in 36 days. She started the work and after 6 days, Leslie joined her. They completed the job in 12 more days. Find the number of days in which Leslie alone can complete it.

Answers

Answered by amitnrw
15

Given : Pam can complete a job in 36 days.

She started the work and after 6 days, Leslie joined her.

They completed the job in 12 more days.

To Find  the number of days in which Leslie alone can complete it.

Solution:

Let say PAM 1 day work = P

Hence total work  = 36P  

Pam worked for 6 + 12 = 18 Days

Work done by PAM = 18P

Remaining working = 36P - 18P  = 18P

Work done by  Leslie  in 12 days  = 18P

=> Work done by  Leslie  in 24 days  =36P

Hence Leslie alone can complete it. in 24 Days.

Learn More:

with P starting the work, working on alternate days P and Q can

brainly.in/question/12303996

With p starting the work, working on alternate days, p and q can ...

brainly.in/question/12364364

Answered by aakankshasolanki70
2

Answer:

24

Step-by-step explanation:

Let say PAM 1 day work = P  

He worked for 36 days => So total work is 36P    

Pam worked for 6 + 12 = 18 Days ,

So done by PAM in 18 Days => 18P

Remaining working for Leslie => Total work - Work done by PAM

i.e. 36P - 18P  = 18P

Now,

Work done by  Leslie in 12 days  => 18P

Work done by  Leslie in 24 days  => 18 * 2 => 36P (Total work)

Hence Leslie alone can complete it in 24 Days.