Paul and Peter can do a piece of work in 50 days and 55 days. They started to work together but Paul leaves after some days and then Peter completed the remaining work in 22 days. Calculate the number of days after which Paul left the work?
Answers
Given:
Paul and Peter can do a piece of work in 50 days and 55 days.
Peter completed the remaining work in 22 days
To find:
The number of days after which Paul left the work
Solution:
In 1 day, the work done by Paul =
and
In 1 day, the work done by Peter =
So, in 1 day, the work done by Paul and Peter together will be =
Let "x" days be the no. of days after which Paul left the work
It is given to us that after working together for "x" days, Paul leaves and Peter completes the remaining work in 22 days. So, we can form the equation as,
⇒
⇒
⇒
⇒
⇒
⇒ 4
Thus, Paul left the work after 15.714 days.
-------------------------------------------------------------------------------------
Also View:
Bindal can finish work in 10 days jindal is twice as efficient as bindal .If they work togher in how many days the work will be finished?
https://brainly.in/question/8757986
Paul and peter can do a piece of work in 60 days, while paul can do it alone in 80 days. how many days will peter take to complete the work alone?
https://brainly.in/question/4786032
The number of days after which Paul left the work is 16
Step-by-step explanation:
The work done by Paul = 1/50
The work done by Peter = 1/55
The number of days after which the Paul leaves be 'x'
Now, the amount of work done by Paul and Peter is given as:
⇒ x[1/50 + 1/55]
The remaining work was completer by Peter in 22 days. Then,
⇒ x[1/50 + 1/55] + 22/55 = 1
x[1/50 + 1/55] = 1 - 22/55
x[21/550] = 33/55
x = 33/55 × 550/21
∴ x = 15.71 ≈ 16 days