Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?
A) 50
B) 100
C) 70
D) 35
Answers
Answered by
0
Q:
Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?
A) 50B) 100C) 70D) 35
Answer: B) 100
Explanation:
Let the Efficiency of pavan be E(P)
Let the Efficiency of sravan be E(S)
Here Work W = LCM(25,20) = 100
Now, E(P+2S) = 100/25 = 4 ....(1)
E(2P+S) = 100/20 = 5 ....(2)
Hence, from (1) & (2) we get
E(S) = 1
=> Number of days Savan alone work to complete the work = 100/1 = 100 days.
Answered by
0
↪hii mate↩
↪here is ur answer ↩
↪⭐option ß) is correct⭐↩
↪explanation↩
⭐→100/25=4✔
→100/20=5✔
→100/1=1⭐
↪here is ur answer ↩
↪⭐option ß) is correct⭐↩
↪explanation↩
⭐→100/25=4✔
→100/20=5✔
→100/1=1⭐
Similar questions
Social Sciences,
7 months ago
Math,
7 months ago
Math,
1 year ago
Math,
1 year ago
English,
1 year ago