person A asnd B can complete a task in 15 days and 10 days respectively . if they work together for 3 days ,how many more days would person A take to complete the remaining task also?
1. 5 days
2. 6 days
3. 7.5 days
4.10.5 days
Answers
Answered by
0
Step-by-step explanation:
A=2/30
B=3/30
A+B= 5/30 =1/6
FOR 3 DAYS = 15/30 remaining part is 1/2=15/30
remaining work will be completed = 2*x= 15
x= 7.5 days