Math, asked by ravenclaw6024, 1 year ago

Person A can complete a job in 48 min while B can complete the same job in 60 min. How long will they take together?

Answers

Answered by 247him
1

26 minutes and  40 seconds

explanation as follows ->

Let J is the amount of Job

Given,

48A = J and

60B = J

Let together they complete job in X minutes

then

X.A + X.B = J

substituting value of A and B  and canceling J

X(1/48 + 1/60) = 1

X = 60 x 48 /(60 + 48) = 26.666 minutes = 26 minutes and  40 seconds