Peter employed five men to develop a computer software and they were able to complete it in 13 days. Had Peter suspended two of them after the fourth day, then what would have been the total number of days in which the work would have been completed?
Answers
Answer:
19
Step-by-step explanation:
the answer should be 19 days
Work will be completed in 19 Days if 5 can complete in 13 days & 2 are suspended after 4 days
Step-by-step explanation:
Peter employed 5 men to develop a computer software
Complete in 13 Days
Number of Man Days Required = 5 * 13 = 65 Man Days
Work completed in 4 Days = 5 * 4 = 20 Man days
remaining Employess = 5 - 2 = 3
Remaining Work = 65 - 20 = 45 Man Days
Number Of Days Further Required = 45/3
= 15 Days
Total number of Days = 4 + 15 = 19 Days
Work will be completed in 19 Days
Learn More:
12 men complete a work in 9 days after they worked for 6 days 6 ...
https://brainly.in/question/11630708
A contractor undertakes to complete a work in 130 days he ...
https://brainly.in/question/11724055
two workers undertake to do a job. 2 hours after the first worker ...
https://brainly.in/question/9188732