Math, asked by tuku21, 5 months ago

please answer this questions:-D​

Attachments:

Answers

Answered by aniii03
1

 \huge \underline \mathtt \colorbox{cyan}{ANSWER:}</p><p>

  1. work done by a in 3 days 3 \div 15 \\  = 1 \div 5 \\  = 0.2

2.work left for b 12 \div 15 \\  = 0.8

3.no. of days b will take3 \div 4 = 12 \div x \\ 3 \times 4 = 12.4 \times 4 = 16 days