Math, asked by Rrrraaaa, 11 months ago

Please answer to the question

Attachments:

Answers

Answered by Alisha12344
1

Answer:

10 days are required to finish the same work

Step-by-step explanation:

Given: No of workers that finish work in 5 days working 2 hrs a day = 10

To find: No of days required by 2 worker to finish same work

             when working 2 hrs per day

Let x be the required no of days.

No of working hours of 10 people = 2 × 5 = 10

No of working hours of 2 people = 5 × x = 5x

No of people and no of working are inversely related to each other.

⇒ 10 × 10 = 2 × 5x

100 = 10x

x = 10

Therefore, 10 days are required to finish the same work by 2 people when working for 5 hrs a day.

HOPE IT HELPS YOU! :D


Alisha12344: Are you in 11th??
Ritiksuglan: ya
Ritiksuglan: n u
Alisha12344: 10th'
Ritiksuglan: okk
Ritiksuglan: change your original dp dear
Alisha12344: Why??
Alisha12344: Bro.. Why should I change my original dp?
Ritiksuglan: hii
Ritiksuglan: not bro
Similar questions