please give a very clear explanation dont use any shortcut
Attachments:
Answers
Answered by
1
let A do work in x days and B do work in y days .
we know,
both work together in (xy)/(x + y) days
hence,
xy/(x + y) = 8 days
now both start work together and after 6 days A left the work .
both do work within 6 days ,
hence,
both do 6/8 part of work in 6days .
rest (1-6/8) part of work doing by only B
hence, 1/4 part of work do by B in 6 days
hence, complete work do by B in 6 x 4 =24 days.
but B do complete work in y days .
so, y = 24 days
24x/(24+x) = 8
3x. = 24 + x
x = 12 days
we know,
both work together in (xy)/(x + y) days
hence,
xy/(x + y) = 8 days
now both start work together and after 6 days A left the work .
both do work within 6 days ,
hence,
both do 6/8 part of work in 6days .
rest (1-6/8) part of work doing by only B
hence, 1/4 part of work do by B in 6 days
hence, complete work do by B in 6 x 4 =24 days.
but B do complete work in y days .
so, y = 24 days
24x/(24+x) = 8
3x. = 24 + x
x = 12 days
john44:
thanks a lot in advance
Similar questions
Accountancy,
8 months ago
Math,
8 months ago
Math,
8 months ago
Social Sciences,
1 year ago
Science,
1 year ago
Social Sciences,
1 year ago
Math,
1 year ago