Math, asked by jhaa45075, 4 months ago

please give answer its very urgent​

Attachments:

Answers

Answered by Anonymous
0

Answer:

45 men do the work in 49 days

1 man will do the same work in 49 × 45 days

= 2205 days

35 men will do the work in 2205/35 days

= 63 days

PLEASE MARK ME THE BRAINLIEST.........

Answered by stutibhatia
0

Answer:

63 days

Step-by-step explanation:

45 men =49 days

so 1men=49/45 days

35men. =x days

so 1men=x/35 days

it is inverse variation

so 49/35=x/45

x =49*45/35

x =7*9

x =63 days

therefore,35 men will complete the work in 63 days

hope it helps!!

plz Mark me as brainliest