Math, asked by purvi8, 1 year ago

please guys........ please solve this question

Attachments:

Answers

Answered by anurag40
1
100 more men should be employed ( 200+100=300)

purvi8: thanks a lot
Answered by Byomkeshbakshi
1
First 130 days are over so only 130 days are left and More 50%work is to be done so 50% of 200 that 100 More men are needed

purvi8: thanks a lot