please please help me i will be really thank full
Attachments:
Answers
Answered by
1
Answer:
12 men work 6 days, that is 12*6=72 workdays to complete the task.
If we have 18 men available, and assume they work the same way, they will also need 72 workdays. But as they are more, the time needed will be 72/18=4 days. So, assuming the task is similar and the working pattern keeps the same, we will finish in 4 days.
Step-by-step explanation:
As same as your queb