Math, asked by smitakumarigaya20, 5 months ago

please solve all the questions I will mark you as brainliest ​

Attachments:

Answers

Answered by uppadagiridhar510
0

Text my personal phone number to ask any of them

Step-by-step explanation:

8639204857

Answered by sajidalli8114
0

Step-by-step explanation:

No:8 Ans

A can complete the work in 12 days.

In one day he can complete 1/12th part

B can complete the work in 15 days.

In one day he can complete 1/15th part.

C can complete the work in 20 days.

In one day he can complete 1/20th part.

When they together , in one day they can complete (1/12+1/15+1/20)part.

Therefore, they will complete the work in 1/(1/12+1/15+1/20) days.

  • 1/(1/12+1/15+1/20)
  • 1/{(5+4+3)/60}
  • 1/(12/60)
  • 60/12
  • 5 days.

Hence, it would take 5 days to complete the work.

Similar questions