Math, asked by jaiprakash111, 1 year ago

please solve it step by step

☺☺

Attachments:

Answers

Answered by siddhartharao77
11

Given that A can complete a work in 10 days.


Work done by A in 1-day = (1/10).


Given that B can complete the work in 12 days.


Work done by B in 1-day = (1/12).


Work done by A and B in 1-day = (1/10) + (1/12)


= 11/60.



Work done by A and B in 3 days = (11/60) * 3


= 11/20.



Remaining work = (1 - 11/20)


= 9/20.



Now,


9/20 of the work completed by B in (12 * 9/20) = 108/20 days.


Therefore, the total time taken = (108/20) + 3


= 168/20


= 42/5


= 8 (2/5) days.





Hope this helps!


siddhartharao77: :-)
siddhartharao77: Thank you Dora!