Math, asked by itzJitesh, 11 months ago

please solve my questions
please don't fake answer​

Attachments:

Answers

Answered by ejjejejdejje
5

1 work done by A in 20 days.

  1. In 1 day,work done is 1/20 of work.
  2. In 5 days, work done is 1/20 ×5=1/4 of work
  3. 1 work done by B in 10 days
  4. In 1 day, work done is 1/10 of work
  5. In 5 days , work done is 1/10×5=1/2 of work
  6. In 5 days, work done by both is 1/4+1/2=3/4
  7. Remaining work is 1-3/4=1/4 (ans)