please solve no 43 to be mark as brainliest
Attachments:
Answers
Answered by
1
HEYA MATE, HERE IS UR ANSWER __________________
Let the total number of men be x .
Days taken by x men to complete the work =50 days .
When 7 more people are added
Number of men= x+7
Days Taken by them =50-10
=40
Since the work is same
We know the formula
work =men×day
therefore
x×50=(x-7)40
50x=40x-280
50x-40x=-280
10x=-280
x=-280/10
x=-28
Since men cannot be negetive ,Therefore ignoring negetive value and taking x=28 .
So number of men originally employed =28.
_______☆☆HOPE THE ANSWER HELPS YOU. ☆☆______☆☆BE BRAINLY ☆☆
Let the total number of men be x .
Days taken by x men to complete the work =50 days .
When 7 more people are added
Number of men= x+7
Days Taken by them =50-10
=40
Since the work is same
We know the formula
work =men×day
therefore
x×50=(x-7)40
50x=40x-280
50x-40x=-280
10x=-280
x=-280/10
x=-28
Since men cannot be negetive ,Therefore ignoring negetive value and taking x=28 .
So number of men originally employed =28.
_______☆☆HOPE THE ANSWER HELPS YOU. ☆☆______☆☆BE BRAINLY ☆☆