Please solve this answer with wording
Attachments:
Answers
Answered by
5
Given :
- 5 persons completes a task in 4 days.
To find :
- We need to find how many days would it take if number of workers is 4.
Assumption :
- Let the number of days be x when number of workers are 4.
Solution :
⠀⠀⠀⠀⠀⠀⠀⠀⠀⠀⠀⠀⠀⠀⠀⠀I case⠀⠀⠀⠀⠀ll case
Number of workers⠀⠀⠀⠀⠀ 5⠀⠀⠀⠀⠀⠀⠀4
Number of days⠀⠀⠀⠀⠀⠀⠀ 4⠀⠀⠀⠀⠀⠀⠀ x
Observing the given values we can say, as we increase the number of workers, time taken to complete the task would decrease.
So, according to the inverse proportionality :
════════════════════════