Please tell: -Anil can do a piece of work in 5 days and ankur in 4 days. How long will they take to do the same work, if they work together?
Answers
Answered by
70
Solution:-
Number of days taken by Anil to complete the work = 5 days
Anil's 1 day work = 1/5
Number of days taken by Ankur to complete the work = 4 days
Ankur's 1 day work = 1/4
Now, work done by Anil and Ankur jointly in 1 day = 1/5 + 1/4
= 9/20
So, Anil and Ankur will take 20/9 days to complete the same work if they work together.
Answer.
Number of days taken by Anil to complete the work = 5 days
Anil's 1 day work = 1/5
Number of days taken by Ankur to complete the work = 4 days
Ankur's 1 day work = 1/4
Now, work done by Anil and Ankur jointly in 1 day = 1/5 + 1/4
= 9/20
So, Anil and Ankur will take 20/9 days to complete the same work if they work together.
Answer.
Answered by
6
Answer:
hey
here your answer
20/9 days
Hope it will help