please tell me this question answer ✍️​

Attachments:

Answers

Answered by Snehpriyanshu
11

Answer:

32 days

Step-by-step explanation:

40 men can do the work in 60 days

then,

1 man can do the same work in =40×60 days

=2400 days

then,

We can find the number of days required to finish the same work by 75 men :

= 2400/75

= 32 days

PLEASE THANKS AND FOLLOW ME

Answered by yashsingha2020
3

Answer:

Given,

40 men finish the work in 60 days.

Therefore, individually we have 40*60 = 2400 units of work.

Now, for 75 workers to complete the work, it will take..

2400/75 = 32 days

Hope this helps you..